Forecasted income
Item |
Amount (CAD) |
Remarks
|
Membership cards |
600 |
Forecasted
|
Donations |
800 |
Forecasted
|
Annual Plan Grant from Wikimedia Foundation for H1 |
22,000 |
Approved
|
Contingency funds for Annual Plan Grant from Wikimedia Foundation for H1 |
2,200 |
Approved; to be returned at the end of exercise
|
Annual Plan Grant from Wikimedia Foundation for H2 |
47,595 |
Approved
|
Contingency funds for Annual Plan Grant from Wikimedia Foundation for H2 |
4,760 |
Approved; to be added to WMCA's reserve funds at the end of exercise
|
Project grant from Environment Canada |
45,000 |
Subject to approval
|
Total |
122,955 |
|
In-kind donations
Item |
Value (CAD) |
Remarks
|
Office space at BAnQ Vieux-Montréal |
18,624 |
Space donation from BAnQ
|
Room for regular workshops at Grande Bibliothèque de Montréal |
5,280 |
Space donation from BAnQ
|
Room for regular workshops at BAnQ Québec |
1,320 |
Space donation from BAnQ
|
Room for regular workshops at Université Laval |
156 |
Space donation from BAnQ
|
Total |
25,380 |
|
Forecasted expenses
Item |
Amount (CAD) |
Remarks
|
Programs |
40,905 |
Funds coming from both SAPG and Environment and Climate Change Canada's grant
|
Capacity building |
4,125 |
Funds coming from SAPG 2018 H2
|
Operating costs |
11,065 |
Funds coming from both SAPG
|
Contractor for capacity building |
36,000 |
Funds coming from SAPG 2018 H2
|
Contingency funds to be returned to Wikimedia Foundation |
2,200 |
Funds coming from SAPG 2018 H1
|
Total |
94,295 |
|
Item |
Amount (CAD) |
Remarks
|
Content, outreach and communities |
2,150 |
|
Indigenous projects |
7,055 |
|
Photographic content |
1,460 |
|
Operating costs |
9,595 |
|
Total |
22,000 |
|
Item |
Amount (CAD) |
Remarks
|
Content, outreach and communities |
3,200 |
|
Indigenous projects |
1,600 |
|
Photographic content |
1,200 |
|
Capacity building |
4,125 |
|
Operating costs |
1,470 |
|
Contractor for capacity building |
36,000 |
|
Total |
47,595 |
|
Grant for Wikidata Meteorological Project from Environment Canada
edit
Item |
Amount (CAD) |
Remarks
|
Project expenses |
22,500 |
|
Total |
22,500 |
|
All funds that are not from a grant will be added to WMCA's reserve funds.